PROJECT UPDATE, August 12th - Joint Construction Project Along Johnson Drive

construction update

JOHNSON DRIVE PROJECT UPDATE - AUGUST 12th: 

  • The parking lots within Roeland Park east of Roeland Dr. will be graded and paved the week of 8/15/2022.
  • Joint repairs will be performed on Johnson Dr. the week of 8/15/2022. There will be periodic lane drops with flaggers at various locations along Johnson Dr. Please drive carefully.
  • During the week of 8/22/2022, Johnson Dr. will be milled and UBAS pavement will be placed on Johnson Dr. the week of 8/29/2022 followed by pavement markings.
  • This schedule is tentative and subject to change due to weather conditions.
    ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Joint Construction Project

Roeland Park & Mission will be partnering on a joint construction project along Johnson Drive from Lamar Ave. to Roe Blvd. Construction is set to begin on July 11th. Improvements will include curb & gutter replacement, spot sidewalk replacement, new UBAS surface treatment as well as new striping. A new sidewalk will be added on the north side of Johnson Drive within Roeland Park’s boundaries. The construction sequence for the project is anticipated to be the following and is subject to change.

July 11: Begin concrete removal on South side of Johnson Dr.

July 11-15: Complete removal and replacement of concrete on south side of Johnson Dr.

July 18: Begin concrete removals on North side of Johnson Dr.

July 18-22: Complete removal and replacement. of concrete on north side of Johnson Dr. to approximately Roeland Dr.

July 25- 29: Complete removal and replacement of concrete on north side of Johnson Dr. from Roeland Dr. to east end of project.

August 1: Asphalt repairs complete in Roeland Park on north side of Road

August 8: Macrotextures are completed on Johnson Drive.

August 15: Construction finishes on Johnson Drive

August 22: Thermoplastic completion of all areas.