Roe Blvd Construction 9.16.2020

The following is a list of updates regarding the Roe Boulevard 2020 Project:

  • Curbs/Driveway complete south of 51st St;
  • Sidewalks complete south of 51st St except small section at 55th St;
  • Streetlighting bases and conduit have been installed... waiting on breakaway bases to arrive to start installing poles;
  • Traffic signals installed at 55th St; Evergy will provide power to the controller this week;
  • Storm sewer work is complete south of 51st St;
  • Milling completed south of 51st St
  • Surface paving to be completed week of October 12th;
  • Pavement striping to be installed towards the end of this week;
  • Sod to be installed in the next 2-3 weeks. 